Invitation to Tender in the open procedure for public procurement 20/17

Inspections of PPA and hydrant networks 

 

 

 

   Invitation For public competition in an open public procurement procedure

     

Orderer's details

Employer:

Montenegrin Electricity Transmission System AD

Information Officer: Rajka Kecojević, B.Com.

Address:

Bulevar Svetog Petra Cetinjskog 18

Postcode: 81000

Headquarters:

Podgorica

PIB (Registration number):  02751372

Telephone: +382 (20) 407 654

Fax: +382 (20) 244-492

Electronic mail (e-mail):

rajka.kecojevic@cges.me

Website:

www.cges.me

II Type of procedure

— open procedure.

 

III Subject of the public procurement

a)      Type of public procurement item

¨ Services

b)     Description of the public procurement item

Inspections of PPA and hydrant networks

c)      CPV – Common Procurement Vocabulary

CPV codes:

50413200-5 Repair and maintenance services for fire-fighting equipment

Pipeline testing services

IV Conclusion of the framework agreement

A framework agreement will be concluded:

¨ to

         ¨ for the subject matter of the procurement as a whole

       

The framework agreement is concluded for a period of: 24 months.

The public procurement contract based on the framework agreement is concluded for a period of 12 months.   

¨ The framework agreement will be concluded with the highest-ranked bidder.

Immutable elements of the framework agreement:

1) subject of the procurement;

2) conditions for participation in the public procurement procedure;

3) the total estimated value of the public procurement;

4) the total estimated value of the procurement items for the first year of application of the framework agreement;

5) the total offered price and the offered individual prices for the first year of application of the framework agreement;

Variable elements of the framework agreement:

¨ the quantity of services to be procured on an annual basis during the term of the framework agreement;

¨ the dynamics of the delivery of the services subject to procurement;

Method of concluding a public procurement contract:

¨ Upon a written request from the contracting authority, the bidder shall submit a clarification of their bid or a new bid in accordance with the terms provided for in the framework agreement.

V Method for determining the subject matter and estimated value of the public procurement:

¨ Estimated value of the procurement item with by concluding the framework agreement

Total estimated value of the public procurement during the term of the framework agreement, including VAT 21.420,00 €.

Estimated value of the public procurement for the first year of the framework agreement:

¨ like Total, estimated values including VAT 10.710,00 €.

VI Possibility of submitting alternative bids

¨ no

VII Conditions for participation in the public procurement procedure

a) Mandatory requirements

Only a tenderer who:

1) is entered in the register with the authority competent for the registration of business entities;

2) has duly fulfilled all its tax and social security contributions obligations in accordance with the law, or the regulations of the state in which it is established;

3) proves that he or his legal representative has not been convicted by a final judgment for any criminal offence acts of organised crime with elements of corruption, money laundering and fraud;

The conditions of paragraph 1 of this point do not apply to natural persons: artists, scientists and cultural creators.

Proof of compliance with mandatory requirements

Compliance with the mandatory requirements is demonstrated by providing:

1) proof of registration with the competent authority for the registration of business entities, with details of the bidder's authorised representatives;

2) a certificate issued by the tax authority confirming that all tax and contribution obligations have been duly declared, calculated and paid up to 90 days prior to the date of the public tender opening, in accordance with the regulations of Montenegro, or the regulations of the country in which the tenderer is headquartered;

3) a certificate from the competent authority issued on the basis of the criminal record, which must not be older than six months as of the date of the public opening of bids;

b) Optional conditions

b1) Financial capacity

Proof of compliance with the economic and financial capacity requirements is provided by submitting:

¨ Not required

b2) Professional and technical competence and staffing capacity

¨

Fulfilling the conditions of professional technical and personnel qualifications in the public procurement procedure service is proven by providing the following evidence:

¨ a list of the main services carried out in the last two years, with values, dates and recipients, along with certificates of services rendered issued by the client or, if the certificates cannot be provided for reasons not attributable to the bidder, a declaration by the bidder regarding the services performed, stating the reasons why they are unable to provide the certificates;

¨ Statements of intent and subject matter of the subcontracting, with a list of subcontractors, or sub-suppliers, including their full details (name, address, percentage participation, etc.).

 

8. Validity of the offer

The validity period of the offer is 90 (ninety) days from the date of the public opening of bids.

 IX Offer Guarantee

¨ to

The bidder is obliged to provide an unconditional, first-demand tender guarantee in the amount of 2% of the estimated value of the public procurement, as a guarantee of their commitment to the tender during the validity period of the tender and for 5 (five) days after its expiry.

X  Place and time of performance of the contract

a) The contract shall be completed within 365 days from the date of its conclusion.

b) The place of performance of the contract is Podgorica, Pljevlja, Berane, Bijelo Polje, Mojkovac, Nikšić, Danilovgrad, Cetinje, Budva, Tivat, Kotor, Herceg Novi, Bar, Virpazar and Ulcinj.

XI Language of the offer:

¨ The Montenegrin language and the other language which is in official use in Montenegro, in accordance with the Constitution and the law.

12. Criteria for the selection of the most favourable offer:

¨ lowest offered pricenbsp;                        &number of points      100   

XIII Time and place for submission of tenders and public opening of tenders

Offers are submitted on weekdays. from 11:00 to 14:00, up to and including the day 19 June 2017 to 11:30 hour

Offers may be submitted:

¨ by direct delivery to the client's archives at 18 Bulevar Svetog Petra Cetinjskog, Podgorica

¨ by recommended delivery with return address at 18 Bulevar Svetog Petra Cetinjskog, Podgorica.

The public opening of tenders, which may be attended by authorised representatives of the tenderers with an attached power of attorney signed by an authorised person, will be held on  19 June 2017 at 12:00, at the premises of the Montenegrin Electricity Transmission System at the address 18 St. Petar Cetinjski Boulevard, Podgorica.

Article 14 Deadline for making a decision on the selection of the most favourable offer

The decision on the selection of the most favourable offer will be made within 90 (ninety) days from the date of the public opening of bids.

XV Other data and conditions relevant to the conduct of the public procurement procedure

Deadline and method of paymentchange

The payment deadline is: 30 calendar days from the date of invoice delivery

The method of payment is by bank transfer. by payment into the supplier's current account.

¨  Financial Security for Public Procurement Contracts

The supplier whose offer is selected as the most advantageous is obliged to provide the client with:

¨ a performance bond in the amount of 5% of the contract value with a validity period of 5 (five) days longer than the agreed service delivery period.