Contract signed for the connection of SE "Prediš" to the transmission system

7 August 2023
IMG 7604 2

On 4 August 2023, a contract was signed in Podgorica for the connection of the 'Prediš' solar power plant, with an installed capacity of 215 MW, to the transmission system, valued at around 180 million euros. The contract was signed by Ivan Asanović, CEO of CGES, and the CEO of 'Renewable Energy Sources' LLC, Rusmin Muslić. The solar power plant will be connected via a 400 kV transmission line to the RP 'Čevo' substation. In addition to the higher connected power that the grid will be able to accept, this technical solution also enables better characteristics of the transmission system as it eliminates the possibility of a simultaneous failure of the 400 kV transmission lines towards Trebinje and Pljevlja, which will have multiple benefits, including an increase in short-circuit power and system inertia.