CGES – SOLAR POWER PLANT
An agreement on the connection of the solar power plant Prediš, whose installed capacity is 215 MW and is worth about EUR 180 million, to the transmission system was signed in Podgorica on 4 August 2023. Agreement is signed by the Executive Director of CGES, Ivan Asanović Executive Director of Obnovljivi izvorni energije doo, Rusmin Muslić.
The solar power plant will be connected via a 400 kV overhead line to the switchgear Čevo. In addition to the higher connection capacity that the network will be able to accept, this technical solution also enables better characteristics of the transmission system because it eliminates the possibility of a simultaneous outage of the 400 kV overhead line to Trebinje and to Pljevlja, which will have multiple benefits, including an increase in short-circuit power and system inertia.