Crnogorski elektroprenosni sistem, da bi održao i poboljšao postojeći kvalitet usluga, u prenosni sistem Crne Gore kontinuirano ulaže značajna sredstva. Tako je ovih dana u TS 220/110/35 kV „Podgorica 1“ ugrađen novi transformator 110/35 kV, snage 63 MVA. The completion of this project has increased the reliability and security of the electricity supply to consumers, whilst also creating the possibility for new connections.
With this project, CGES has completed the long-term investment activity of increasing the transformation capacity at the 'Podgorica 1', 'Podgorica 3', and 'Podgorica 4' substations. and 'Podgorica 5', thereby raising the quality of electricity transmission for more than two-thirds of Podgorica's consumption to a higher level.
On this occasion, we would like to highlight that all electrical and construction works were entrusted to the services within CGES, which carried out the task to a high standard and within the scheduled timeframe.
The total value of the investment is around 800 thousand euros.